Question: Review the case study and form a Gantt chart. Task Name Duration Start Finish Predecessors Assigned To % Complete Status Comments Initiating & Planning 26d

Review the case study and form a Gantt chart.

Task Name Duration Start Finish Predecessors Assigned To % Complete Status Comments
Initiating & Planning 26d 10-01-23 11-03-23
Create Project Charter 7d 10-01-23 10-09-23
Identify & Document Project Requirements 7d 10-10-23 10-18-23 2
Create High Level Project Plan 7d 10-19-23 10-27-23 3
Conduct Risk Assessment 4d 10-30-23 11-02-23 4
Conduct Kick off meeting 1d 11-03-23 11-03-23 5
Executing, Monitoring, and Controlling 8d 11-06-23 11-15-23
Human Resource Planning 5d 11-06-23 11-10-23
Hire Extra Help 2d 11-06-23 11-07-23 6
Global Training Plan 3d 11-08-23 11-10-23 9
Operations Planning 3d 11-13-23 11-15-23
Establish Store Holliday Hours 1d 11-13-23 11-13-23 9, 10
Sales Planning(Local & Corporate) 1d 11-14-23 11-14-23 12
Decorations Plan 1d 11-15-23 11-15-23 13
Battle Planning (Shoplifting, Stockouts, etc) 2d 11-15-23 11-16-23 12, 13
Create Social Media Calendars 1d 11-17-23 11-17-23 15
Create Readiness Report for CEO 1d 11-20-23 11-20-23 16
Launch Christmas Campaign 1d 11-21-23 11-21-23 17

The project duration is 127 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!