Question: Review this Earned Value Data. How is it performing? Cum Jan Feb Mar April May June July Aug Sept Oct Nov Dec PV 300 800

Review this Earned Value Data. How is it performing? Cum Jan Feb Mar April May June July Aug Sept Oct Nov Dec PV 300 800 1500 2400 3300 3700 5000 6500 8500 10400 12300 12700 EV 300 900 1700 2800 4000 4700 6100 7800 AC 280 780 1460 2100 2700 2900 4000 5400 Group of answer choices Behind schedule and over budget. Behind schedule and under budget. Ahead of schedule and under budget Ahead of schedule and over budget