Question: Rich James, Program Office Director, has developed the tasks, durations, and predecessor relationships in the following table for Disaster Recovery Team deployment (DRT). To solve
Rich James, Program Office Director, has developed the tasks, durations, and predecessor relationships in the following table for Disaster Recovery Team deployment (DRT). To solve this problem, calculate the expected completion time and variance for each activity, draw a network diagram, complete a forward and backward pass, identify the critical path. Follow the step-by-step solution approach in Gray and Larson text, Chapter 7, Appendix 7.1 called PERT.
What is the probability of completion of the project before week 39?
| Time estimates (in weeks) | ||||
| Activity | Immediate predecessor | Optimistic | Most likely | Pessimistic |
| A | - | 4 | 8 | 10 |
| B | A | 2 | 8 | 24 |
| C | A | 8 | 12 | 16 |
| D | A | 4 | 6 | 10 |
| E | B | 1 | 2 | 3 |
| F | E,C | 6 | 8 | 20 |
| G | E,C | 2 | 3 | 4 |
| H | F | 2 | 2 | 2 |
| I | F | 6 | 6 | 6 |
| J | D,G,H | 4 | 6 | 12 |
| K | I,J | 2 | 2 | 3 |
Group of answer choices
Due to rounding, between 31.50% and 36.68%
Due to rounding, between 5.71% and 6.65%
Due to rounding, between 7.85% and 8.69%
Due to rounding, between 8.79% and 9.8%
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts