Question: Risk ID 1 2 3 4 5 6 7 8 9 10 Probability (%) GRK628828 40 70 75 50 30 60 90 20 30

Risk ID 1 2 3 4 5 6 7 8 9 10


Risk ID 1 2 3 4 5 6 7 8 9 10 Probability (%) GRK628828 40 70 75 50 30 60 90 20 30 10 Impact (ZAR) 83 010 6 484 84 434 86 383 2 246 85 865 16 075 33 430 7444 25 040 5.1 Calculate the Average Impact for each of the risks using a non-aggregated approach. 5.2 Calculate the Average Impact the risks using an aggregated approach. 5.3 Explain what this value means for this organisation? (10 marks) (5 marks) (5 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Risk Analysis 51 Average Impact NonAggregated Approach This approach calculates the average impact for each risk individually Theres no overall averag... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!