Question: ___________ risks, are risks that are left over, so to speak, from the risk occurance itself or left over after the risk responses have been
___________ risks, are risks that are left over, so to speak, from the risk occurance itself or left over after the risk responses have been planned.? (select the best answer)
| A. | Trigger | |
| B. | Residual | |
| C. | Secondary | |
| D. | Control |