Round up all dollar values to the nearest dollarRound up all index values to the 2 decemial places.ES of task A is day _____?ES of task F is day ______?The project duration is _____?BAC is _____?AC is_____?PV______?EV_______?CPI_________?SPI is_______?EAC_____?Please answer as soon as possible. Thank you

1. Project C data Task DurationPredecessor(s) $Budget Status at (Days) the end of day 20 B 8 Start 4,000 Completed and spent 5,000 A 3 B(FS+3) 3,000 Completed and spent 2,000 5 B(FS+6) , 4,000 Completed A(SS+4) and spent 3,500 F 5 A, E 3,000 Not started and spent 1,000 C 4 F(SS-2) 2,000 10% done E(SF+10) and spent 500 D 3 C 2,000 30% done and spent 1,000 G 7 D 7,000 Not started End - G Use Day 1 method to develop a Gantt Chart The status date is at the end of day 20