Question: Sam is managing a project which has a total planned value ( PV ) of 3 0 0 , 0 0 0 . After 4
Sam is managing a project which has a total planned value PV of After months, the actual costs incurred turned out to be Sam is trying to find out, how he can limit the actual cost of the project. Out of the following options, which option explain actual costs best?
Question Select one:
a
Actual cost can be four times the planned value
b
Actual cost can be three times the planned value
c
Actual cost can be two times the planned value
d
The AC will not have an upper limit
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
