Question: Suppose you are managing a software development project. The project is expected to be completed in 8 months at a cost of $10,000 per month.
Suppose you are managing a software development project. The project is expected to be completed in 8 months at a cost of $10,000 per month. After 2 months, you realize that the project is 30 percent completed at a cost of $40,000. You need to determine whether the project is on-time and on-budget after 2 months.
a. What is the budgeted at completion cost estimate?
b. What is the actual cost after two months?
c. What percent of the project was planned to be completed after 2 months?
d. What is the actual project completion percentage after 2 months?
e. Calculate the Planned Value (PV) after 2 months:
f. Calculate the Earned Value (EV):
g. What is the cost variance?
h. What is the schedule variance?
i. What does the cost variance and schedule variance tell you?
- Compute the Cost Performance Index (CPI):
- Compute the Schedule Performance Index (SPI)
- What do the CPI and SPI tell you?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
