Question: Scenario A: An assembly line has three work stations. Demand exceeds capacity, and the line is in full operation. Station 1 takes 20 minutes to
Scenario A: An assembly line has three work stations. Demand exceeds capacity, and the line is in full operation. Station 1 takes 20 minutes to complete the tasks that have been assigned to it to assemble 1 unit of product. Station 2 takes 30 minutes to complete the tasks assigned to it to assemble 1 unit, Station 3 takes 25 minutes to complete the tasks assigned to it to assemble 1 unit. Assuming a 35-hour work week, what is the weekly capacity of the production line?