Question: Scenario A: An assembly line has three work stations. Demand exceeds capacity, and the line is in full operation. Station 1 takes 2 0 minutes

Scenario A: An assembly line has three work stations. Demand exceeds capacity, and the line is in full operation. Station 1 takes 20 minutes to complete the tasks that have been assigned to it. Station 2 takes 30 minutes to complete the tasks assigned to it, Station 3 takes 25 minutes to complete the tasks assigned to it.
Where would one expect to see an accumulation of WIP inventory?
Question 15 options:
WIP inventory will accumulate before Station 1
WIP inventory will accumulate before Station 3
WIP inventory will accumulate before Station 2
there will be no accumulation of WIP inventory, since demand exceeds capacity to assemble products

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!