Question: Scenario: According to Hungry Koala case study, its project scopes are enhancing a new mobile application for Hungry Koala and providing a training to Hungry
Scenario: According to Hungry Koala case study, its project scopes are enhancing a new mobile application for Hungry Koala and providing a training to Hungry Koalas employees, riders, and relevant parties regarding the usage of the application.
In the process to complete the project, Hungry Koala needs to purchase some parts of software from its supplier, unfortunately, both parties have an argument during the meeting as they cannot agree on price so that the supplier refuses to trade with Hungry Koala. As a result of this, the company needs to seek to buy parts from others, and this is expected to take at least three (3) weeks. As a result of this, Hungry Koalas top management is worried that it will directly affect in time, cost and quality constraint for the project.
H. Change Control Policies and Procedures
The purpose of this change management procedure is to manage change requests so that approved changes will be controlled, ensuring the project remains on schedule, within budget and provides the agreed deliverables. The primary objectives of change management are to
manage each change request from initiation through to closure
process change requests based upon direction from the appropriate authority
communicate the impact of changes to appropriate personnel
allow slight changes to be managed with a minimum of overhead.
Question 1:
(a) Use a provided table of Decision Matrix to analyse if the scope change will impact on established time, cost, and quality of the project in accordance with the companys change control policies and procedures (This is in section H of a Hungry Koala Case Study).
(b) Interpret numeric information to determine whether this will negatively affect to timelines and outcomes against project scope.
Guideline: You are required to rate in both rows (Project manager and project sponsor). You are encouraged to think in both side opinion as if you were them that you would analyse and decide to monitor the scope change.
Table A: Decision Matrix
Note: please rate by using number 1-5 (1 = not impact on while 5 = severely impact on)
|
|
| Increase Budget | Increase Time | Increase risk |
| The impact of changes and delay in parts of software | Decision by Project manager
|
|
|
|
| Decision by Project Sponsor |
|
|
|
Note: please rate by using number 1-5 (1 = not impact on while 5 = severely impact on)
(c) Following your answer from part (a & b), if you were a top management of Hungry Koala, what you would decide to minimise its impact on the deadline, budget, and quality requirements according to change control procedures.