Question: Scenario Your organization has won a tender to create a new Software as a Service product, and you're in charge of the project. You decide
Scenario
Your organization has won a tender to create a new "Software as a Service" product, and you're in charge of the project. You decide to use a Gantt chart and networking diagram to monitor the progress. Use the activity table makes the Gantt chart and Networking diagram
You start by listing all the activities that have to take place, and you estimate how long each task should take to complete.
(Marking scheme:
- Activity Name enlisted. (important)
- starting date from table. (important)
- ending date from table. (important)
- Predecessors (Important)
- Gantt chart
- Network Diagram
| Task | Length | Predecessors |
| A. High level analysis | 1 week | - |
| B. Selection of server hosting | 1 day | A |
| C. Configuration of server | 2 weeks | A |
| D. Detailed analysis of core modules | 2 weeks | B |
| E. Detailed analysis of supporting modules | 2 weeks | C |
| F. Development of core modules | 3 weeks | D,E |
| G. Development of supporting modules | 3 weeks | D,E |
| H. Quality assurance of core modules | 1 week | F |
| I. Quality assurance of supporting modules | 1 week | G |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts