Question: Schedule the following activities using CPM: IMMEDIATE PREDECESSOR ACTIVITY A B D E A B C.D D F EG TIME (WEEKS) 2. 5 4 3

Schedule the following activities using CPM:
Schedule the following activities using CPM:
Schedule the following activities using CPM: IMMEDIATE PREDECESSOR ACTIVITY A B D E A B C.D D F EG TIME (WEEKS) 2. 5 4 3 4 1 1 2 G H a. What is the critical path? A-B-D-F-G-H A-B-D-E-H O A-C-E-G-H O A-C-E-F-G-H b. How many weeks will it take to complete the project? Number of weeks c. Which activities have slack, and how much? OB.3 weeks: C. 1 week:F.4 weeks. OB. 1 week:H. 3 weeks:F.2 weeks. OC.4 weeks:F. 2 weeks: G.2 weeks