Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR Comedia: cm.png% AABCDDEE ABCD F G BECH TIME (WEEKS) F Esmedia: cm.png% G 3543 6

Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR Comedia: cm.png% AABCDDEE

Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR Comedia: cm.png% AABCDDEE ABCD F G BECH TIME (WEEKS) F Esmedia: cm.png% G 3543 6 435 b. What is the critical path? OA-C-E-H OA-B-D-E-H O A-B-D-F-G-H OA-C-E-F-G-H c. How many weeks will it take to complete the project? Number of weeks