Question: need C Schedule the following activities using CPM: IMMEDIATE PREDECESSOR ACTIVITY A B D E F G H TIME (WEEKS) 2 3 5 4 A

need C Schedule the following activities usingneed C

Schedule the following activities using CPM: IMMEDIATE PREDECESSOR ACTIVITY A B D E F G H TIME (WEEKS) 2 3 5 4 A B D D F EG 2 3 7 b. What is the critical path? A-C-E-H A-B-D-E-H A-B-D-F-G-H A-C-E-F-G-H c. How many weeks will it take to complete the project? X Answer is not complete. Number of weeks d. Which activities have slack, and how much? OA. 4 weeksi B . 1 week :D. 2 weeks. B. 2 weeks :D . 1 week: E 4 weeks. C. 2 weeksi F. 2 weeks: G. 2 weeks. >