Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A B B C.D D F E.G b. What is the critical path? A-B-D-E-H

Schedule the following activities using CPM:
Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A B B C.D D F E.G b. What is the critical path? A-B-D-E-H A-C-E-F-G-H BCDEFGH 23547237 A-C-E-H A-B-D-F-G-H c. How many weeks will it take to complete the project? Number of weeks d. Which activities have slack, and how much? C. 2 weeks F.2 weeks 1 A. 4 weeks 1 B. 1 week B. 2 weeks D. 1 week G. 2 weeks. D. 2 weeks. E. 4 weeks