Solve the problem below with your team members, and answer the questions. Submit one Word file with your names and solutions. Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) 1 B 4 IC A 3 D B 2 IE C, D 5 F. D INNU 2 G IF 2 . E, G 3 a. Draw the network path. b. What is the critical path? c. How many weeks will it take to complete the project? d. Which activities have slack and how much