Question: Schedule the following activities using CPM ACTIVITY IMMEDIATE PREDECESSOS TOE EERS) 3 6 2 A CO 0 O H E. 2 b. What is the

Schedule the following activities using CPM
Schedule the following activities using CPM ACTIVITY IMMEDIATE PREDECESSOS TOE EERS) 3 6 2 A CO 0 O H E. 2 b. What is the critical path? O A-B-D-F.GH O A-B-D-E-H O A-C-E-F-G-H O A-C-E-G-H c. How many weeks will it take to complete the project? Number of weeks d. Which activities have slack, and how much? OB. 2 weeks Picture D. 1 week OE. 3 weeks Picture H. 2 weeks OC. 10 weeks w Picture E. 6 weeks