Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) 3 A B D : E 6 A B C&media:cm.png? D D F E%media:cm.png$

Schedule the following activities using CPM:
Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) 3 A B D : E 6 A B C&media:cm.png? D D F E%media:cm.png$ G F G 4 3 H 5 b. What is the critical path? O A-C-E-H O A-C-E-F-G-H O A-B-D-F-G-H O A-B-D-E-H c. How many weeks will it take to complete the project? umber of weeks