Question: Problem 5-8 (Algo) Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) 3 A A A B C D D E F G

Problem 5-8 (Algo) Schedule the followingProblem 5-8 (Algo) Schedule the following

Problem 5-8 (Algo) Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) 3 A A A B C D D E F G H 10 UA4 A4 EG b. What is the critical path? O A-B-D-F-G-H A-B-D-E-H O A-C-E-H O A-C-E-F-G-H c. How many weeks will it take to complete the project? Number of weeks d. Which activities have slack, and how much? OC. 3 weeks ;F. 1 week: G. 1 week. O A. 1 week: B. 2 weeks :D. 4 weeks. OB. 3 weeks :D. 2 weeks i E. 4 weeks