Question: Schedule the following activities using CPM: table [ [ ACTIVITY , IMMEDIATE PREDECESSOR,TIME ( WEEKS ) ] , [ A , - , 3

Schedule the following activities using CPM:
\table[[ACTIVITY,IMMEDIATE PREDECESSOR,TIME (WEEKS)],[A,-,3],[B,A,4],[C,A,9],[D,B,2],[E,C,D,7],[?bar(F),D,3],[G,F,4],[H,E,G,5]]
b. What is the critical path?
A-B-D-F-G-H
A-B-D-E-H
A-C-E-H
A-C-E-F-G-H
c. How many weeks will it take to complete the project?
Number of weeks
d. Which activities have slack, and how much?
B,2 weeks; C,3 weeks; E,4 weeks; H,1 week.
B,3 weeks; D,3 weeks; F,3 weeks; G,3 weeks.
B,3 weeks; C,2 weeks; F,1 week; H,2 weeks.
 Schedule the following activities using CPM: \table[[ACTIVITY,IMMEDIATE PREDECESSOR,TIME (WEEKS)],[A,-,3],[B,A,4],[C,A,9],[D,B,2],[E,C,D,7],[?bar(F),D,3],[G,F,4],[H,E,G,5]] b. What

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!