Question: Schedule the following activities using CPM: table [ [ ACTIVITY , IMMEDIATE PREDECESSOR,TIME ( WEEKS ) ] , [ A , - , 3
Schedule the following activities using CPM:
tableACTIVITYIMMEDIATE PREDECESSOR,TIME WEEKSABACADBEDGH
b What is the critical path?
ABDFGH
ABDEH
ACEH
ACEFGH
c How many weeks will it take to complete the project?
Number of weeks
d Which activities have slack, and how much?
B weeks; C weeks; E weeks; week.
B weeks; D weeks; F weeks; G weeks.
B weeks; C weeks; F week; H weeks.