Question: Schedule the following activities using CPM: Table 2 ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 8 B A 4 C A 4 D C

Schedule the following activities using CPM:
Table 2
ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A
8
B
A
4
C
A
4
D
C
8
E
B, D
2
F
D
6
G
E. F
2
Question 25(1 point)
What is the critical path? (Show your diagram and calculations)
A-C-D-F-G
A-B=E-G
A-B-D-F-G
A-C-D-E-G
A-B-D-E-G
Question 26(1 point)
How many weeks will it take to complete the project?
28
24
35
20
32
Question 27(Bonus)(1 point)
E
What is B slack time?
\table[[16],[14],[18],[12],[19]]
 Schedule the following activities using CPM: Table 2 ACTIVITY IMMEDIATE PREDECESSOR

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!