Question: Schedule the following activities using CPM: Table 2 ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 8 B A 4 C A 4 D C
Schedule the following activities using CPM:
Table
ACTIVITY IMMEDIATE PREDECESSOR TIME WEEKS
A
B
A
C
A
D
C
E
B D
F
D
G
E F
Question point
What is the critical path? Show your diagram and calculations
ACDFG
ABDFG
ACDEG
ABDEG
Question point
How many weeks will it take to complete the project?
Question Bonus point
E
What is B slack time?
table