Question: Table 2 ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 18 B A C A 4 D C 8 E B,D 2 F D 6 G E,F

 Table 2 ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 18 B A
C A 4 D C 8 E B,D 2 F D 6
G E,F 2 What is the critical path? (Show your diagram and

Table 2 ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 18 B A C A 4 D C 8 E B,D 2 F D 6 G E,F 2 What is the critical path? (Show your diagram and calculations) A-C-D-F-G A-B-E-G A-B- A-B-L A-C-D-E-G Question 26 (1 point) How many weeks will it take to complete the project? 28 35 32 20 24 What is B slack time? 14 16 19 18 12