Question: Schedule the following activities using CPM: Table 2 ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 8 B A 4 C A 4 D C

Schedule the following activities using CPM:
Table 2
ACTIVITY
IMMEDIATE PREDECESSOR
TIME (WEEKS)
A
8
B
A
4
C
A
4
D
C
8
E
B, D
2
F
D
6
G
E, F
2 What is the critical path? (Show your diagram and calculations)