Question: Schedule the following activities using CPM: Table 2 ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 8 B A 4 C A 4 D C
Schedule the following activities using CPM:
Table
ACTIVITY
IMMEDIATE PREDECESSOR
TIME WEEKS
A
B
A
C
A
D
C
E
B D
F
D
G
E F
What is the critical path? Show your diagram and calculations