Question: Schedule the following activities using CPM: table [ [ ACTIVITY , IMMEDIATE,PREDECESSOR,TIME ( WEEKS ) ] , [ A , - , , 5

Schedule the following activities using CPM:
\table[[ACTIVITY,IMMEDIATE,PREDECESSOR,TIME (WEEKS)],[A,-,,5],[B,A,,3],[C,A,,4],[D,B,,6],[E,,, D,8],[F,D,,2],[G,F,,4],[H,,, G,3]]
b. What is the critical path?
A-C-E-F-G-H
A-B-D-E-H
A-C-E-H
A-B-D-F-G-H
 Schedule the following activities using CPM: \table[[ACTIVITY,IMMEDIATE,PREDECESSOR,TIME (WEEKS)],[A,-,,5],[B,A,,3],[C,A,,4],[D,B,,6],[E,,, D,8],[F,D,,2],[G,F,,4],[H,,, G,3]] b.