Question: Schedule the following activities using CPM: table [ [ ACTIVITY , IMMEDIATE PREDECESSOR, table [ [ TIME ] , [ ( WEEKS )
Schedule the following activities using CPM:
tableACTIVITYIMMEDIATE PREDECESSOR,tableTIMEWEEKSABACADBECmedia:cmpngFDGDHFEmedia:cmpng
b What is the critical path?
c How many weeks will it take to complete the project?
Number of weeks
Schedule the following activities using CPM:
tableACTIVITYIMMEDIATE PREDECESSOR,tableTIMEWEEKSABACADBECmedia:cmpngFDGDHFEmedia:cmpng
b What is the critical path?
ABDEH
ACEFGH
ABEH
ABDFGH
c How many weeks will it take to complete the project?
Number of weeks
D NOT SHOWN ON SCREEN BUT RLLY NEED HELP WITH THIS QUESTION
Which activities have slack, and how much?
a E week; H weeks
b C weeks; E weeks
c B week; D weeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
