Question: Schedule the following activities using CPM: table [ [ ACTIVITY , IMMEDIATE PREDECESSOR, table [ [ TIME ] , [ ( WEEKS )

Schedule the following activities using CPM:
\table[[ACTIVITY,IMMEDIATE PREDECESSOR,\table[[TIME],[(WEEKS)]]],[A,-,3],[B,A,4],[C,A,5],[D,B,4],[E,C%media:cm.png%,8],[F,D,6],[G,D,4],[H,F,5],[,E%media:cm.png%,]]
b. What is the critical path?
A-B-D-E-H
A-C-E-F-G-H
A-B-E-H
A-B-D-F-G-H
c. How many weeks will it take to complete the project?
Number of weeks
Schedule the following activities using CPM:
\table[[ACTIVITY,IMMEDIATE PREDECESSOR,\table[[TIME],[(WEEKS)]]],[A,-,3],[B,A,4],[C,A,5],[D,B,4],[E,C%media:cm.png%,8],[F,D,6],[G,D,4],[H,F,5],[,E%media:cm.png%,]]
b. What is the critical path?
A-B-D-E-H
A-C-E-F-G-H
A-B-E-H
A-B-D-F-G-H
c. How many weeks will it take to complete the project?
Number of weeks
D. NOT SHOWN ON SCREEN BUT RLLY NEED HELP WITH THIS QUESTION
Which activities have slack, and how much?
a. E,1 week; H,2 weeks
b. C,5 weeks; E,2 weeks
c. B,1 week; D,3 weeks
 Schedule the following activities using CPM: \table[[ACTIVITY,IMMEDIATE PREDECESSOR,\table[[TIME],[(WEEKS)]]],[A,-,3],[B,A,4],[C,A,5],[D,B,4],[E,C%media:cm.png%,8],[F,D,6],[G,D,4],[H,F,5],[,E%media:cm.png%,]] b. What is

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!