Question: SECTION B - Answer ANY THREE ( 3 ) questions in this section. [ 6 0 MARKS ] QUESTION 2 ( 2 0 marks )

SECTION B - Answer ANY THREE (3) questions in this section. [60 MARKS]
QUESTION 2(20 marks)
A project life cycle is concerned with sequencing activities in stages to achieve the projects outcomes. With reference to
any project of your choice, examine the significance of the planning stage within the life cycle and highlight the primary
outputs of this stage.
QUESTION 3(20 marks)
You are presently working with the Engineering Department projects office for eThekwini Municipality, and the City
Manager has tasked you with outlining the criteria for selecting engineering-related projects. Explain your response with
practical examples.
QUESTION 4(20 marks)
Four Squares Productions, a firm hired to coordinate the release of the movie Pirates of the Caribbean: On Stranger
Tides (starring Johnny Depp), identified 14 activities to be completed before the release of the film. The tasks in weeks
are provided Table 4.1.
ACTIVITY IMMEDIATE PREDECESSORS TIME (Days)
A -6
B -2
C A 6
D A 8
E B, C 9
F D 3
G D 6
H E, F 4
I G, H 6
J I 5
K I 9
L J 4
M K 2
N L, M 8
a) How many weeks in advance of the film release should Four Squares have started their marketing
campaign?
(10 marks)
b) Which are the activities that need to be prioritised to deliver the marketing campaign project within the
expected time?
(10 marks)
QUESTION 5(20 marks)
Darrel Smith, the project manager at Group Five, seeks advice on strategies for accurately identifying project risks.
Discuss the contents of your report, detailing the approaches he can employ

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!