Question: SECTION B ANSWER ANY THREE (3) QUESTIONS QUESTION 2 [20 MARKS] A project comprises of 12 activities which have the following durations and dependencies. (a)

SECTION B ANSWER ANY THREE (3) QUESTIONS QUESTION

SECTION B ANSWER ANY THREE (3) QUESTIONS QUESTION 2 [20 MARKS] A project comprises of 12 activities which have the following durations and dependencies. (a) Draw a network diagram for the activities set out above and determine the critical path. [15 marks] (b) Calculate the minimum time required to complete the project? [5 marks] Page 5 of 6