SECTION B ANSWER ANY THREE (3) QUESTIONS QUESTION 2 [20 MARKS] A project comprises of 12 activities which have the following durations and dependencies. Activity Dependency Duration (weeks) A 1 B A 5 C B 5 D C 7 E D 5 F E 5 G C 3 H G 3 F 5 J C 13 K J 5 L I,K,H 3 (a) Draw a network diagram for the activities set out above and determine the critical path. [15 marks] (b) Calculate the minimum time required to complete the project? [5 marks] Page 5 of 6