Question: See chapter 4, page 101, question 5. The data for activities of the project is shown below: Immediate Activity Predecessor A Time (weeks) 6 B.

See chapter 4, page 101, question 5. The data for
See chapter 4, page 101, question 5. The data for
See chapter 4, page 101, question 5. The data for activities of the project is shown below: Immediate Activity Predecessor A Time (weeks) 6 B. A 3 17. D 2 E B, D 4 F D 3 G EF 7 Click Save and Submit to sment mit: Question Completion Status: F D 3 G E, F 7 What is the critical path? O A-C-D-E-G O A-C-D-F-G O A-B-E-G O A-B-D-G