Question: See the given task table of the upcoming IT System upgrade project. Assuming that the project team will work a standard working week ( 5

See the given task table of the upcoming IT System upgrade project. Assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks start as soon as possible. Which path is the critical path? (You may use a piece of paper to draw the PERT chart to calculate the critical path).
M_exam_Critical_path_question.JPG
Group of answer choices
ABEGHI
ABCFGHI
ABDFGHI
AECDFEI
ABCEGHI