Question: Select all that apply Which statements are correct about the influence that a planning horizon has upon project estimates? Multiple select question. Estimating at the
Select all that apply Which statements are correct about the influence that a planning horizon has upon project estimates? Multiple select question. Estimating at the conceptual phase of a project degrades as planning gets more granular. Near term event estimating is more accurate than long range planning. Estimating is more accurate after the individual work packages have been defined. Long duration projects have better estimates due to averaging of results over time