Question: Which statements are correct about the influence that a planning horizon has upon project estimates? Multiple select question. Long duration projects have better estimates due
Which statements are correct about the influence that a planning horizon has upon project estimates? Multiple select question. Long duration projects have better estimates due to averaging of results over time. Estimating is more accurate after the individual work packages have been defined. Near term event estimating is more accurate than long range planning. Estimating at the conceptual phase of a project degrades as planning gets more granular