Question: Which statement is not correct about the influence that a planning horizon has upon project estimates? Group of answer choices Estimating at the conceptual phase
Which statement is not correct about the influence that a planning horizon has upon project estimates? Group of answer choices Estimating at the conceptual phase of a project degrades as planning horizon gets longer. Near-term event estimating is more accurate than long-range planning. Long-duration projects have better estimates due to averaging of results over time. Estimating is more accurate after development of a WBS