Question: Select correct option A new product development project has four levels in the work breakdown structure and all work packages are at level 4 of
Select correct option

A new product development project has four levels in the work breakdown structure and all work packages are at level 4 of the structure. Using the Bottom up method of estimating at what level should the estimates be developed? O a. Level 3 O b. Level 1 O c. Level 4 O d. Level 2