Question: Explain your choice? 1. A new product development project has four levels in the work breakdown structure and has been sequenced using a network diagram.

Explain your choice? 1. A new product developmentExplain your choice?

1. A new product development project has four levels in the work breakdown structure and has been sequenced using a network diagram. The duration of work packages have been received. What should be done NEXT? (Single choice: 1 out of 4; 2 points) 1. A. Ask for more budget B. Begin with the work breakdown structure C. Finalise the cost estimation D. Finalise the schedule