Question: A new product development project has four levels in the work breakdown structure and has been sequenced using the precedence diagramming method. The activity duration

A new product development project has four levels in the work breakdown structure and has been sequenced using the precedence diagramming method. The activity duration estimates have been received, What should be done NEXT? A. Create an activity list. B. Begin the work breakdown structure. C. Finalize the schedule. D. Compress the schedule.