Question: Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority

Sequence the jobs shown below by using a Gantt
Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority order 1, 2, 3, 4 Job 2 Work center A3, B2, C2 C/2, A/4 B/6, A/1, C13 C/4, A/1, B2 Due date (hours) 24 16 32 Which one is the correct sequence based on the shortest processing time (SPT)? (this scenario has multiple questions, please save your calculation 02-14.3 O 8.3.4.1.2 Oc2.3.4.1 OD. 1-4.3.2 O E 3-1-4-2