Question: Sergio's client ask him to fast track a software development project. How can Sergio comply with this request? A . Overlapping the longest durations not
Sergio's client ask him to fast track a software development project. How can Sergio comply with this request? A Overlapping the longest durations not on the critical path. B By overlapping some activities on the critical path. C By reducing lag times by D By sequencing the highest risk activities.