Question: Sergio's client asks him to fast-track a software development project. How can Sergio comply with this request? A by overlapping some activities on the critical
Sergio's client asks him to fast-track a software development project. How can Sergio comply with this request?
A
by overlapping some activities on the critical path
B
by overlapping the longest-duration activities not on the critical path
C
by reducing lag times by 10 percent
D
by sequencing the highest-risk activities