Question: Sergio's client ask him to fast track a software development project. How can Sergio comply with this request? A. Overlapping the longest durations not on
Sergio's client ask him to fast track a software development project. How can Sergio comply with this request? A. Overlapping the longest durations not on the critical path. B. By overlapping some activities on the critical path. C. By reducing lag times by 10%. D. By sequencing the highest risk activities.