Question: Sewer Line Calculations A . Draw the given information and your solution on engineering paper at a scale of 1 ' ' = 2 0

Sewer Line Calculations
A. Draw the given information and your solution on engineering paper at a scale of
1''=20.00' in a neat, orderly manner.
B. Assume that the service line must extend perpendicular to the building. The required
service line grade is to be 6.000%
C. Determine the distance ' X ', and the distance from the building (' Y ') to the 45 bend of
the service line.
D. Determine the total length of service line from the building to the main in order to match
the flowline elevation of the service line to the main at the required grades.
E. Determine the flowline elevation at the point where the service line meets the main.
(NOTE: Horizontal bends will be 45 ells.)
Sewer Line Calculations A . Draw the given

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!