Question: Shirts are made in a process with a single resource. There are two types of shirts. The resource s processing time for the first type

Shirts are made in a process with a single resource. There are two types of shirts. The resources processing time for the first type is 8.5 minutes and demand for this type is 32 shirts per hour. The resources processing time for the second type is 0.91 minutes and demand for this type is 35 shirts per hour. There are 6 workers at this resource.
What is the implied utilization (%) of this resource?
Note: Round your answer to 1 decimal place.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!