Question: Shirts are made in a process with a single resource. There are two types of shirts. The resource's processing time for the first type is

Shirts are made in a process with a single

Shirts are made in a process with a single resource. There are two types of shirts. The resource's processing time for the first type is 500 seconds and demand for this type is 0.23 shirts per minute. The resource's processing time for the second type is 2,800 seconds and demand for this type is 0.16 shirts per minute. There are 11 workers at this resource. Instruction: Round your answer to one decimal place. What is the implied utilization (%) of this resource? %

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!