Question: Shirts are made in a process with a single resource. There are two types of shirts. The resource s processing time for the first type

Shirts are made in a process with a single resource. There are two types of shirts. The resources processing time for the first type is 1,600 seconds and demand for this type is 0.54 shirts per minute. The resources processing time for the second type is 87 seconds and demand for this type is 0.4 shirts per minute. There are 10 workers at this resource.
What is the implied utilization (%) of this resource?