Show all work for problems 4 and 5.
4. Given the following network:
(a) What is the critical path?
(b) How long will it take to complete this project?
(c) Can activity B be delayed without delaying the completion of the project? If so, how many days?
5. Given the estimated activity times below and the network in Problem 4 above
\table[[Activity,a,m,b
 Show all work for problems 4 and 5. 4. Given the