Question: Show all work. Given an activity's optimistic, most likely, and pessimistic time estimates of 3,5 , and 11 days respectively, compute the PERT expected activity
Show all work.
Given an activity's optimistic, most likely, and pessimistic time estimates of 3,5 , and 11 days respectively, compute the PERT expected activity time for this activity. 5.67 5.50 6 6.16