Question: Show all work. Given an activity's optimistic, most likely, and pessimistic time estimates of 3,5 , and 11 days respectively, compute the PERT expected activity

Show all work. Given an activity's optimistic, most likely, and pessimistic timeShow all work.

Given an activity's optimistic, most likely, and pessimistic time estimates of 3,5 , and 11 days respectively, compute the PERT expected activity time for this activity. 5.67 5.50 6 6.16