Question: QUESTION 9 Given an activity's optimistic, most likely, and pessimistic time estimates of 4 , 6 , and 1 4 days respectively, compute the PERT

QUESTION 9
Given an activity's optimistic, most likely, and pessimistic time estimates of 4,6, and 14 days respectively, compute the PERT expected activity time for this activity.
DA)7
B)6
C)8
D)9
)7.5
QUESTION 10
 QUESTION 9 Given an activity's optimistic, most likely, and pessimistic time