Question: QUESTION 9 Given an activity's optimistic, most likely, and pessimistic time estimates of 4 , 6 , and 1 4 days respectively, compute the PERT
QUESTION
Given an activity's optimistic, most likely, and pessimistic time estimates of and days respectively, compute the PERT expected activity time for this activity.
DA
B
C
D
QUESTION
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
