Question: Given an activity's optimistic, most likely, and pessimistic time estimates of 4 , 1 0 , and 2 2 days respectively, compute the PERT expected

Given an activity's optimistic, most likely, and pessimistic time estimates of 4,10, and 22 days respectively, compute the PERT expected activity time for this activity.
11
14
22
32
none of the above