Question: show work 224. Using the Capital Asset Pricing Model, what is a project's rate of return, if b = 1.5, average market return is 8%,
show work
224. Using the Capital Asset Pricing Model, what is a project's rate of return, if b = 1.5, average market return is 8%, and a comparable U.S. government security is 3%? A) 3% B) 8% C) 10.5% D) 12%